Diary of a New Radio Control Model
Flying Site by Tom Laird & Jim McGlynn
Aerial photos by Martin Gibbs, Forth Valley Soarers | ||
I recorded our experiences in building a new flying site in the hope that it may be of use to anyone else considering the same path. In the beginning was the realisation that our (then)
current flying site was not filling all our needs.
It was the wartime airfield at Kirknewton near Jim McGlynn
and I had spent a considerable amount of time
knocking on farmers' doors to no success and had all
but given up. |
||
However, we
placed an advert in the "Scottish Supermart"
and this resulted in an invitation to visit the farm
in question. Following a tour, one particular site
was earmarked. It was 1/2 mile from the nearest
house, had a hard road up to a car park for a dozen
cars, and pilots would have the sun to their back
when flying. Pretty good?
Not quite! The grass was 2 feet tall, and the whole
place was a peat bog on top of a clay sub-soil.
That's a pretty bad combination. On the upside,
the farmer said he would cut and roll the grass, we
could fence off the area, and an Astro
Turf, tarmac or concrete runway was not a problem. |
||
Week 2 We went back a
week later with 3 other members to have another
look. The nice flat bit was running North/South but
the approach would take a plane too close to the
village so that runway was out of the question. The
East / West was on a
slope and that did not look the best solution
either. However, the slope would help the ground
drain a bit better so we went for it. Our reasoning
was partly that Woodsprings
is also on boggy land and they have done it, so why
couldn't we? Week 3Sunday
morning. Went up with Jim for a
couple of hours. Took
up a dozen bags of top-soil in case they're
required. Took some plastic sheeting and
started hauling the grass to the end of the runway.
Dug out about 20 metres
of the North / South drain which was clogged up.
That should help things. It's
impressive how much can be accomplished in such a
short time. Week 4 Put advert in
"Scottish Supermart"
for a petrol fly-mo. Buy it on the Wednesday
evening. Go up on the Sunday and cut half of the car
park and the first part of the runway, whilst Jim
and John start digging a new East / West drain along
the side of the cut grass area. The place still
looks better in the dark. We need money and we need
more helpers, but the place is not really far enough
on to impress people. It's getting dark at |
||
Week 5Phone around
for mini-digger prices, hard-core prices and field
drain prices. Jim phones the local council for road
scrapings so we get put on their backlog. Put advert
in the "Scottish Supermart"
for field drain. Wednesday: They've got the ad in the wrong section so had to re-send it. Pick up some pallets on the way home. They need creosoteing before they can be used. More money and another job to be done. |
||
It has rained
pretty well all week. Went up on the Saturday for 4
hours and cut another area of the car park, and
another part of the runway. The trick here is to cut
it, rake it, then leave
it for an hour to dry, then cut again. The ground is
pretty wet after the rain so no chance of getting
the tractor and a 4 & 1/2 ton roller on the
case. Dug out another 10 metres of the new
East/West runway drain. The peat is very
wet so it cuts easily. The water is now starting to
flow so perhaps we're making progress. Took
time of to fly the glider for 1/2 an hour.
Lots of thermals due to the
standing water. Must
get a noise test done soon for the power people. Sunday. Should
have picked up some Astro-turf.
However, our contact has not been back to us, and we
don't have a lorry anyway. Wives stop play so we
can't do any work on the field. Spend some time
repairing a crack in the fly-mo's
skirt. Jim informs me that he has a contact for a
motor roller and that it can be delivered. How we
get it across to the runway is another matter since
the ground is very wet in places. Week 6It has rained
solidly all week but surprisingly, the site is no
wetter than on previous visits. Wednesday: We
get two replies from the advert for field drain, but
nothing has come of them. Thursday: Jim
informs me that he has about a dozen 2 x 2 slabs for
the pilot stance area. Discuss using old engine oil
on the pallets but reject as too messy. Sunday
afternoon: Jim, John and I are joined by the SAA
secretary, Harry West. We finish clearing the main
North / South drain, and cut two new drains across
the width of the runway. Water is flowing freely in
all of them so we are starting to see some result
for our efforts. Need to dig at least one more
across the top and down the other side of the slope. We do a noise
test with my Mascot but it a fairly quiet engine (OS
40 LA) so maybe it is not giving a true impression.
Objectives for
next week: Must
get three aircraft up in the air. Do
the third cross runway drain and start on
the other length-ways one. I took some
photographs for the web site but they were pretty
poor. Sunday
evening: The farmer phones me. He has 100 metres
of drain pipe. Also, he will dump some shale on the
entrance, AND he will cut more of the long grass. I
ask him for some advertising blurb about his farm
for our web site. |
||
Week 7Tuesday: Visit
the local garden centre.
A 25kg bag of grass seed, 50% rye is £100. Visit the
greenkeepers at the
local golf course and get a contact name at Sports
Turf Services at Newbridge and
call them for advice. They have a seed that will
cost about £40 for enough to do the area. If there
is a lot of moss we really need to hire a scarifier
to cut through it. Also, it seems that coatings of
sand will be beneficial
as it will be absorbed into the peat, thereby
breaking it up. Also it will eventually get absorbed
into the clay thereby acting as a route for the
water to flow through. We are now too late to sow
grass seed as the frost last night would have killed
it. However, we may need to put down some fertiliser
over the winter. The salesman
lives near the site so he will go have a look at the
site. He will call me middle of next week he says.
Yeah, right! I'm still waiting. It rains all
week. However, when I go up on the Sunday, it is no
worse than the week before. Unfortunately, rain
stops play. All we get done is to dig a new 10metre
drain which was half full of water by the time we
left Week 8Monday:
Professor Spoor phones to discuss progress and
drainage techniques. Thursday: Jim
has found a mini-digger and driver for £50 a day. This is the
weekend of Jim's 40th birthday so there
is absolutely no chance of going up this Sunday. Okay! I'm
addicted. I went up on Sunday afternoon and dug
another 15metres of ditch. Week 9Jim went up on
Monday and finished the top drain. He also cleared
about 10metres of the cut grass. Sunday. 4 people turn up AND the
mini-digger which proceeded to dig 60 metres
of ditch before a hydraulic leak stopped play. All
the cut grass was cleared from the site, and about
50metres of peat from the drains was removed. The
site is now starting to look a bit better. It's
still wet, but that's not surprising as we have had
another week of serious rain. Week 10The deep drain
which the mini-digger had dug had filled with water
on the East side of the slope. This drain was taken
further East to meet up
with an existing drain, and the water started to
clear. This amount of water must also have been
cleared from the North side of the slope rather than
continue down onto the runway. Another lesson
learned. 1" of rain
fell last night so the whole place was very wet. But
so is every other field in the county. The
mini-digger could not put in our next drain, so he
joined our South drain to our East one, thereby
completing a trench all the way around the runway.
Any water in the runway can now only be rainfall. 3 visitors
came up to the site and (surprise, surprise) a
contractor to quote for a tarmac runway. We also have
had an offer of a heavy duty petrol strimmer. I gave the
farmer a copy of the development plan which broke
the site down into bite-sized chunks, with proposals
and estimates for each. "No problem, very
professional" he said.. Week 11You guessed
it! Another week of rain.
Its now very frosty at
night, and there is no heat in the sun. When the
frost melts, the grass gets wet, and stays wet. The Sunday was
the day earmarked as the "Open Day" for potential
members. About 7 people including a Civil Engineer
turned up. He examined the site, and promised us a
written report. We extended the main barrier drain
and allowed the water to drain off. A lot of the
peat from the cross-runway drains was removed, and
by the end of the day, the place was looking pretty
tidy. We also got some flying done which was nice
for a change. The
development plan is now almost complete and is only
awaiting the last of the quotes. Next week is the SAA's A.G.M. so work will
probably slow down until we hear from the lottery /
Awards for All application which we will be
submitting. The advert is
almost ready, and the locations
for the posters has been agreed. Week 1225 copies of
the advert have been made and these should get
distributed throughout the area over the next 2
weeks to libraries (note that you should approach
the central librarian and he/she will get the
posters distributed). The first
committee meeting has been set for the 10th
Nov. Membership
currently stands at 10 but needs to be a lot higher. Spoke with
planning department and environmental health.
Planning application stuff has arrived so that needs
looked at. Saw some
people looking at our advert on the noticeboard
at the SAA's A.G.M. so
at least word will start to get around about us. Spoke to the
Chairman of the Woodsprings
Club. They have 10 feet of peat below them, and a
nice 100m x 10m tarmac runway. Total cost to date:
about £50K. They also do an airshow
every year. Week 13 (oh-oh, unlucky
for some) The "Code of
Practice for Model Aircraft Noise" has arrived.
Basically it's all just common sense. The first
committee meeting was held. Application forms for
the local model shop are required, and the New
Members Welcome Pack will be put together over the
next couple of weeks. The adverts
are now being distributed. We currently
have one new person (Gordon's work colleague)
showing an interest. The bank
account has now been opened. The lottery
application continued to be tweaked and has now gone
for review by our contact in West Lothian District
Council. There are 2 versions of the plan: one for a
3 year development and on for a 5 year development.
Sunday was
"meet-the-neighbours"
day. We spoke to about 20 residents of the local
village and left letters with contact phone numbers.
The response in all cases was very positive. The
other 26 will be done in due course. We also did a couple of test flights. Well, 1 test flight and 1 test crash. A clevis pin sheared and my Mascot spun in vertically from about 50 feet. Messy! The model was buried up to its wings in the peat. The prop wasn't even broken. Some minor damage was incurred when the front wheel sprung back when it hit the ground, and a minor bruise on the wing, but it's still intact. (The prop went straight in the bin anyway). |
||
The "before & after" pictures of the path from the car park to the runway. | ||
Weeks 14 & 15 (Xmas
& New Year) Not a lot has
happened over these two weeks. The advert is now in
the local model shops. The advert is also in the
local libraries and sports centres
in the area. Another 30
letters have been photo-copied to hand out to the neighbours in the local
village. We have had
some feedback on the lottery application. Basically
we need to make some changes to the constitution
regarding the assets if the club packs up, and we
need to do more work on how we will try to bring new
people into the hobby. There is now a
sum of money earmarked as "Youth Development Fund"
shown on the budget for the next 3 years. We have
the BMFA's teacher
guide and model price list, as well as hard copies
of the BMFA handbook. Week 16The major
event this week was to get the lottery application
approved and sent off. This was done. A letter was
sent out requesting informal planning approval and
press releases have been sent to 4 of the local
newspapers. We have had one new membership enquiry,
with a further 1 nibbling at the edge. We also have a
proper drawing / plan of the runway construction,
courtesy of the Civil Engineer who kindly visited a
couple of weeks ago. We have also found a squad who
will lay the concrete properly for us. We have a
letter from the farmer saying that "we can use and
develop the site, and that barring any unforseen
circumstances, we have the site for the next 5, if
not 10 years". The 17th
Jan in the afternoon is the next scheduled visit to
the site. Lindsay Dickie,
Don Imrie and Ian McLaren should also be there
to give us their views on the suitability of the
site. I now feel
that we have turned a corner, and that things are
starting to come together. Its
been a long and hard slog, with high levels
of frustration due to the rain, but very enjoyable
nevertheless. We are learning a lot, and hopefully
others can learn from our experience. Week 17 A press
release was sent out to 4 of the local newspapers.
One called me and said the wanted to do a full blown
article with photographs. Consequently I sent them a
copy of our "Welcome Pack" and some supporting
information about model flying in general. The
photo-shoot was arranged for the Saturday and it
dawned bright and cold. About a dozen people turned
up with model including Martin Gibbs with a 4metre
Algebra, Ian McLaren
with a £5000 7 foot Mirage and Lindsay Dickie
who gave a display (in a 30MPH wind) with his OS70
powered AcroWot. Following the
adverts for new members in the Scottish Supermart
we have received 4 calls from prospective members. Iain Weymss
has donated a C.S.M. R/C model flying simulator to
the club. This is now available and anyone with a PC
can borrow it. The "Welcome
Pack" has now gone out to most members. |
||
Errecting the electric fence in Year 2 (see later) | ||
Week 18The newspaper
article turned out to be a double-page centre
spread in colour. It
was pretty accurate with a little bit of reporters licence thrown in for good
measure. We received 5 phone calls, one person being
the original Chairman in 1952, and represented about
10 others. Another person represented about 6 others
who were having a hard time getting trained. Not bad
if they all join up. All adverts
are now distributed, and all "Welcome Packs" have
been sent out. Busy week. The council
planner has been out to look at the site, and sees
no problems. Consequently, we will be making a
formal planning application ASAP. The current
thinking is that we want all membership fees in by
the 12th Feb so that we know where we
stand financially, with a committee meeting on the
14th to draw up a detailed plan. We will
hear from the planning people on the 26th
March and expect to start work on the first week-end
in April. The concrete will hopefully go in at the
beginning of May, depending on the weather. Currently we
have 12 members and 21 other "Welcome Packs" have
been sent out. I am now getting slightly concerned
that the car park could get quite crowded, and could
become a limiting factor on how many members we
accept this year, or until we extend the car park.
Our 5-year budget shows 14 members this year, rising
to 20 next year. The car park as it stands can take
about 12 cars, and parking on the roadside is not an
option. If only all problems were as nice to have as
this one. Week 19Sunday saw an
early morning attack on the site with a strimmer.
Jim cut a path straight across from the car park to
the runway. Those reeds didn't stand a chance until
the chord run out so we'll need to get a new one and
go back again. Dave Gillan
followed up with a 12 metre
drain to let the standing water soak away. The drain
had an immediate effect and should result in a drier
pathway to the runway. We also fully
measured the site and posts were hammered in to mark
out the drive, car park, path and runway. Week 20The tension
mounts. Will our grant application be successful, or
will we need to do it the hard way? Will we have
enough members to do it the hard way? How many
people are thinking they can just wait for the
runway to appear, and then join? Will the rain ever
stop? And will the wind ever fall below Gale Force? The "Open
Morning" was successful with 11 adults + 2 youths
turning up, plus 2 new phone calls in the evening.
All "Welcome Packs" have now gone so another dozen
need photo-copying. The Community
Centre has been booked
for the 28th Feb. The land-fill
contractor did not turn up - surprise, surprise.
These guys really are a pain - if the
are not interested, why do they not just
say so? Iain Wemyss
has tracked down the local councilor and we'll see
if there is any other grant money available. The runway
construction plans have now arrived, and site plans
are being done for the planning application. Sunday:-
phoned an entry to the local newspaper regarding the
club. I intend using this to keep non e-mail people
up to date with progress. Week 21The big day
arrived. We received a letter from the Scottish
Sports Council awarding us £4306 under the "Awards
for All" scheme. Detailed planning now needs to
start asap. On Sunday
distributed the remaining letters to the neighbours.
Only 1 person voiced concern, but we still need to
be careful. Spoke to 2
possible contractors and arranged to get back in
touch prior to next site visit. One lives nearby so
he's handy. Iain Wemyss
has sourced a couple of other grant applications so
they need looking at. Another new
member has joined us. A good
week for a change. Week 22 Not a bad week
when all is said and done. Plenty
of sunshine but very cold, and a lot of rain as
well. All the local fields still have lots
of standing water so we are no worse than anyone
else. The main event
this week was to send off the planning application.
A last minute action was to measure the distance
from the runway to the road which Jim managed to do
somehow. The magic date is the 26th March when we
will hear from the planning committee. This in not
really a concern since the planners have already
done a preliminary assessment and reckon we will be
okay. Nevertheless, you can't go spending £5000 on
someone's say-so. Detailed
planning is now underway so that we can start work
at the beginning of April. I finally got
around to adding buttons to the web site, and
improving the "No Frames" version. I've also got us
linked from a few other local sites. This is
important - think about where the locals will browse
and get your club's web site linked from there. Weeks 23 & 24 There's not a
lot to report this week. We had to send more new
maps to the planning committee so we may not here
until the 26th April. Major
disappointment. We are in
discussions regarding the indoor exhibition. Jim has
a meeting tomorrow to discuss but the overall idea
is to do a 3-way presentation between us, the
Scottish Jet Team and the Scottish Aerobatics Team. I have
installed the R/C simulator training software on the
local community centre's
computers for those non-computer members. This turns
out to be a GOOD IDEA.
|
||
The North grass runway built in year 2, see later. | ||
Week 25 We have
applied for and received £300 from the West Lothian
Sports and Recreation Association to buy a Real
Flight simulator and a further CSM one. Hopefully we
will have these working at the exhibition. The exhibition
at Week 26 It's been
another hectic week. On Monday sent out 10 press
releases regarding the Jim has had
extensive discussions with the concrete squad. They
are all working 12 hour shifts, so we may have to do
the whole job ourselves. Now there's a surprise! Iain is trying to get concrete
prices, and Started making
up the data sheets for the exhibition so that the
public know what they are looking at. These will be
printed on card and will stand beside each model. Scanned a
couple of pictures of the aerobatics team and
uploaded them to the web site. Think that we should
really have a presentation page on one of the web
sites for each of the teams:-
names, pictures, models, successes etc. On Saturday
morning I went over to Scoonie
Hobbies (60 mile round trip) to pick up the box of
raffle prizes they donated for Got
some nice photos & data from Martin Gibbs for
the exhibition. Week 27
This was the BIG WEEK. The planning application was successful and the first indoor static model exhibition was held at the Freeport Shopping Complex. The exhibition was a success and we are on cloud nine. (and as usual there are plenty to choose from J) |
||
Week 28 The big green
button has been pushed and things lurch into
operation. Sunday: The HiMac is delivered to the
site and parked away from prying eyes. Make a final
phone call to the contractor and speak with the
driver. All systems are go.
At last! ( |
||
We knew
exactly where to look but they had sunk into the mud
hence the wasted hour. Very
frustrating. By Tuesday: Rain all day with some dry
spells. Very cold wind.
07:40 Pick up
the himac driver while
Jim visits the demolition site to find out when our
rubble will arrive, only to discover that the rubble
we had been promised would not be forthcoming unless
we could move it ourselves. Jim arranges a tipper
contractor. He also chases up the vibrating roller
hire company who had been told LAST WEEK that we
needed the roller. By the middle of the afternoon we
gave up chasing. (How DO these companies survive???) I shoot off at
Wednesday: ( ( (Jim 08:00)
Meet lorry driver, load up the rubble and deliver to
the site ( ( ( ( ( ( ( ( ( ( The path from
the car park to the runway is now covered with
rubble and is bedded in. ( (
|
||
Picture showing the main runway just after the tarmac was laid. The leading edge was subsequently smoothed off. | ||
Thursday ( ( This was a
very frustrating day. We could not get hold of the
rubble provider to find out what was going on. It
was also a day of heavy rain, so the open clay was
getting broken up. Although we tried hard, 3 men
alone could not move 20 tons of type 1 quickly
enough to protect it. Ian Weymss
did a great job in boarding up the porta-wreck
which has now been promoted to Porta
Cabin since it is now weatherproof, has its door
back on and is a nice shade of green thereby merging
into the background. Friday: Another
frustrating day! Colin was on-site at Colin and I
moved some of the rubble down to the gate entrance
as this was starting to get very soft and mushy,
while Jim dug a drain from the bottom of the runway
to let the standing water clear. Colin honed
his D.I.Y. skills by painting the (now boarded up)
windows. At Saturday John Donaldson
arrived about Sunday John again
looked after the fort and supervised the unloading
of 4 loads of rubble. Things are now moving,
although about a week behind schedule. About |
||
Week 29 Meet John
Donaldson at the Teram
suppliers at We had
arranged to meet one of the demolition contractors
working in the area, but as is now the norm, HE DID
NOT SHOW UP!! A phone call found out that he had
been called to an emergency fire in Tuesday Back to work
for a rest. My real work that is. |
||
Week 30 - Week 34 This was
another exciting period. The local ice rink was
being demolished and after negotiations, we took
delivery of about 800 tons of rubble. The demolition
company also put in a 32 ton Hi-Mac to spread the
rubble. In addition, a local cement works got in
touch asking if we could use their scrapped cement
tiles. (Xmas has come early). We took delivery of 20
pallets worth, wrapped in polythene and moved by
fork lift to the exact spot and arranged to take
them for the forseable
future. |
||
By the end of
all this we had a 50m x 20m car park, a 50m x 3m
path to the runway, and a 65m x 7m runway foundation
complete with pilot stance and starter box area.
Special mention goes to Colin Hume who almost lived
on the site, co-ordinating
deliveries and keeping the main road clean and the neighbours happy. All we have to
do now is clean up the site and lay
the tarmac. We're getting close now, and the end is
in site. Week 35 Sunday was
earmarked for the tidy-up. The morning was nice and
saw about 6 or 7 early risers getting stuck in.
Unfortunately rain stopped play about Week 36 We received a
bit of bad news. Our original planning permission
was for a concrete runway, but we submitted a
request to change to tarmac. The council wrote back
saying "we would introduce an urban element into a
rural area". It's a bog for goodness sake. Not only
that, but our planner had gone on holiday for 3
weeks. Negotiated
our rent payment as a brand new roll of Teram
instead of cash.
That's more money in the runway fund. |
||
Week 38 Put out a
request for next year's fees to bolster the runway
fund and got an immediate donation of £100. "Ask and
you might be
lucky and receive" is something we have
learned. More tidy up work was carried out, and the long grass attacked with the strimmer. The sun cannot dry out the ground if the grass is too long and drains are our best friend on this site. Friday: GREAT NEWS!!!! A letter arrived from the planners. They accepted our
points and gave permission for tarmac. All systems
are now "go!" There is
light at the end of the tunnel. Its
all been worth it. All we need is another couple of
hundred pounds. Week 39This was
reasonably easy week. All I had to do was take a
half-day off work to meet the estimator from the
local council to explain what we wanted. Week
40
The quote arrives from the council and the go-ahead is given. |
||
Week 42Arrives
at site around The runway
should have been 6 metres
wide. The foundation was, because we checked it, but
they only did the top surface at 5 metres.
|
||
Week 43 - 44Negotiated
100 tons of road bottoming as compensation for the
narrow runway.
Week 45Bottoming
material arrived. Farmers
tractor was borrowed and all the bottoming material
was spread down either side of the runway, and at
either end to give good run-off areas. Week 46The farmers
quad bike and harrows was borrowed and all the open
clay was leveled off. We had the official opening
day looming so we really had to get the site tidied
up. This just seemed to take ages. Everytime
you looked there was something else needing done.
|
||
Year 2 Erected a 500m electric fence. Built
a grass runway adjacent to the tarmac one. (scraped out old top surface, put in drains,
put in new top soil, re-seeded). |
||
Year 3 Foot &
Mouth stopped play for most of the year. Plans to
surface the access road and car park put on hold. |
||
Year
4 Submitted a second planning application and applied for a second "Awards for All" award to allow us to install a safer car park, and a container to use as a club house. These are particularily useful for our older members who can get inside out of the cold. |
||
Year
5 Submitted a third "Awards for All" award to bring the site up to competition level. The resulting work involved digging out a new pits area and re-filling with top soil, and importing, laying and leveling new top soil on the South runway. We also put in a cross wind runway. This was put in with the intention that training would not be impacted if the wind was not beginner friendly. |
||
In 2011 we made a major investment to installing a stock-proof fence around the perimeter with the aim of keeping the sheep out. This has paid dividends as the site is a lot cleaner and healthier. |
||
2012 saw two improvements: the path from the starter tables to the pilots stance was paved, | ||
and two assembly tables were donated and the area mono-blocked and fenced off. | ||
Advice